Mechanical Permits

NOW ACCEPTING ELECTRONIC APPLICATIONS
In response to COVID-19, we are not accepting paper applications and paper documents at this time. We are still open for business and here to accept new applications and documents for existing applications electronically.
Applicants must submit all necessary documentation, similar to in-person permit application submissions; incomplete submissions will not be processed. All fees may be paid online.
Mechanical permits include plumbing, drainage, hot water heating and fire sprinklers. The District of West Vancouver does not issue gas permits.
All plumbing permits must be taken out on your behalf by a provincially-qualified contractor unless you can satisfy the plumbing inspector that you have the knowledge and skills appropriate to do the work.
Applications for commercial, multi-family and tenant improvements require two sets of drawings.
Mechanical Permit
Required Mechanical Inspections
Drainage
An inspection of damp-proofing, drain-tile and rainwater leaders with all joints primed and glued and the pipe bedded in gravel with the top of the pipe showing (see Drainage Notes ). (See WorkSafeBC Policy re Excavation Construction Site Safety). Note: Drainage Permit required for installation and inspection of drain tile, foundation damp-proofing, sanitary and storm sewers, and on-site water service lines.
Sewers
An inspection of the sewer pipe firmly bedded in the trench, test on, and before any backfill. (See WorkSafeBC Policy re Excavation Construction Site Safety)
Water Service
An inspection of the pipe in the trench, sand bedding or sleeve, and the water turned on.
DWV and Water Pipes
All DWV and water pipes must be tested and visible for inspection. This inspection must pass before framing inspection can be called.
Heating
All pipes tested with air and visible for inspection. Permanent waterproof labels to be in place on all loops showing: zone number, exact footage, the room served, and sub-area for multiple loops in one room. Home runs and headers will be inspected at random times and do not require a separate inspection. Heating pipe inspections must be passed before framing inspection can be called. Design and installation to be by the current TECA standards. See Hot Water Heating Inspection Requirements - Installation Guide
Sprinkler
All pipes to be tested to 200 PSI and inspected before covering any pipe. No piping permitted to touch electrical wires of any kind. Maintain clearances from pot lights. Frost protection inspection required by the plumbing inspector. Sprinkler rough-in and frost protection must be passed by the plumbing inspector before calling for the framing inspection.
Bathtubs and showers
Bathtubs and showers to be properly supported, filled with water, and inspected before drywall.
More Information
West Vancouver does not issue or inspect gas installations. For details, please visit:
Contact
We are still open for business and here to accept new applications and documents for existing applications electronically.
Permits & Inspections Department
Staff are here to assist you by phone, Monday–Friday, 8 a.m. to 4:30 p.m.
For general inquiries:
Email applications and documents to:
Apply & pay for mechanical permit online
You must have a MyDistrict profile and a valid West Vancouver or North Shore Inter-Municipal Business Licence prior to applying for a permit. Call 604-925-7152 to obtain a business licence.
Mechanical Permit: Plumbing Permit
Mechanical Permit: Drainage Permit
Mechanical Permit: Hot Water Heating Permits (including Geothermal)