Update: December 2016

Completion of construction and site restoration work is expected in early 2017, weather dependent. Thank you for your patience while this important work is completed.

Background

The sanitary lift station located near 6250 Imperial Avenue has reached its end-of-life and is scheduled for upgrades in 2016.

Construction is scheduled to begin the week of March 14 and continue until the end of July.

The lift station forms an integral part of the sanitary sewer collection system. Upgrades will include:

  • replacement of existing pumps
  • improvements to backup power
  • the addition of a remote monitoring system

The District has retained a third party contractor to complete this important work.

Affected area

Imperial Avenue and Wellington Avenue, south of Marine Drive