Roads and Utilities Capital Projects Timetable

This timetable shows anticipated 2017 construction activities for the District’s roads, water, sewer, and drainage projects. These projects are scheduled to take place this year, pending Council approval of capital project funding.

Please note: start dates and duration can vary due to weather, contractor availability, and other variables.

The District aims to provide advance notice of construction activity as much as possible. On-site signage is installed in advance where traffic impacts are expected, and those in the immediate area receive notice letters with information about construction schedule and anticipated impacts.

We recognize that construction may cause inconvenience, and work to minimize the impact on residents and businesses while this important work is completed.

Last updated: December 21, 2016
 

Project Title   Description   Start Date   Duration (est)   Status
                 
Major Projects                
Kings Avenue & Duncan Street/13th Street from Kinds to Inglewood   Coordinated water main upgrades and road reconstruction.   spring   water: 16 weeks
roads: 3 weeks
  completed
Nepal Crescent & Ottawa Avenue   Coordinated water main upgrades and road reconstruction.   spring   water: 24 weeks
roads: 3 weeks
  completed
4500 block Woodgreen Drive   Coordinated water main upgrades and road reconstruction.   summer   water: 23 weeks
roads: 3 weeks
  half of the project was completed this year
Spirit Trail Western Section   Complete trail connection from Exit 0 to Royal Ave   spring        
Orchill Road Parking & Pedestrian enhancements   Complete final road repairs. Clubhouse and community centre parking improvements, full road reconstruction, pedestrian area improvements began fall 2015.   spring   in progress   complete
                 
Road Improvements                
4400 and 4500 block Keith Road   Final asphalt pave. Water main completed in 2015.   spring   4 weeks   complete
Altamont Cres & Altamont Place   Final asphalt pave. Water main completed in 2015.   spring   3 weeks   complete
1000 block Keith Road   Final asphalt pave. Water main and pedestrian safety improvements completed in 2014.   spring   1 week   complete
1100 to 1200 block Keith Road   Final asphalt pave. Water main and pedestrian safety improvements completed in 2015 and 2014.   spring   1 week   complete
27th Street and Queens Avenue   Road resurfacing   spring   1 week   complete
1000 blk laneway between Esquimalt & Fulton   Laneway resurfacing   spring   2 days   in progress
Hadden Creek Culvert Road Reconstruction   Final road rehabilitation. Culvert completed in 2015.    summer/fall   1 week   complete
15th St (Mathers Ave to Queens Ave)   Road resurfacing   summer   5 days   complete
24th St (Marine Dr to Haywood Ave)   Road resurfacing   summer   5 days   2017
Finch Hill (Chippendale Rd to Pinecrest Dr)   Road resurfacing   spring   5 days   2017
Skilift Road (Westhill to Folkestone)   Road resurfacing, sidewalk, curb   summer   6 weeks   2017
21st Street (Queens to Westhill)   Sidewalk, curb   summer   3 weeks   complete
2600 Bellevue   Rehabilitate retaining wall   summer   3 weeks   complete
24th Street and Bellevue   Improve railroad crossing, following CN railroad maintenance.   summer   3 weeks   complete
                 
Sewer & Drainage                
The Cove Lift Station Replacement   Upgrade existing pump station   fall   TBD   in progress
Imperial Ave Lift Station Replacement   Upgrade existing pump station   spring   16 weeks   delays in commissioning the lift station. expecting to wrap up early next year. paving will be weather dependent.
Citrus Wynd Treatment Facility Upgrades   Sewage treatment facility upgrades   summer/fall   2 months    
Willow and Claymore Creek Outfalls   Creek and foreshore drainage improvements   TBD   TBD    
Eagle Lake Access Road Drainage   Drainage improvement and road repair   fall 2015   2 weeks   complete
McDonald Creek Culvert at Fulton Ave   Culvert repair and drainage improvement   summer   2 weeks   complete
Trash & Debris Screen Program   Replacement of debris screens and trash racks as needed in storm drainage system   spring/summer/fall   4 months   various locations
Condition Assessment Program   CCTV and smoke-testing program   spring/summer   4 months  

various locations

Stormwater Detention Basin Dredging   Regular maintenance of stormwater & drainage system   spring/summer/fall   on-going, weather-dependent   various locations
Storm and Sewer Mainline Rehabilitations   Regular maintenance of stormwater and sewer systems   spring/summer/fall   on-going, weather-dependent   complete
2500 Palmerston Avenue Sewer Replacement   Replacement of sanitary and storm sewer mains through laneway and Right of Way between 2500 blocks of Palmerston and Queens Avenue   late summer   TBD   in progress: restoration deferred to 2017
Water                
4600 Caulfeild Drive   Water main upgrades   summer/fall   15 weeks   in progress - end of December completion
Inglewood Check Valve Installation   Water main valve replacement including trench and road patch   summer/fall   1 week    

 

×