Roads and Utilities Capital Projects Timetable

This timetable shows anticipated 2018 construction activities for the District’s roads, water, sewer, and drainage projects. These projects are scheduled to take place this year, pending Council approval of capital project funding.

Please note: start dates and duration can vary due to weather, contractor availability, and other variables.

The District aims to provide advance notice of construction activity as much as possible. On-site signage is installed in advance where traffic impacts are expected, and those in the immediate area receive notice letters with information about construction schedule and anticipated impacts.

We recognize that construction may cause inconvenience, and work to minimize the impact on residents and businesses while this important work is completed.

Last updated: January 15, 2018
 

Project Title   Description   Start Date   Duration (est)   Status
                 
Major Projects                
Spirit Trail Western Section   Complete trail connection from Exit 0 to Royal Ave   spring   6 weeks   started
2600 block Queens Avenue   Coordinated water main upgrades and road reconstruction   spring/summer   water: 22 weeks   started
1300 block Cammeray Road   Coordinated water main upgrades and road reconstruction   spring/summer   water: 10 weeks   started
1825 Palmerston Avenue & St. Denis Road   Coordinated water main upgrades and road reconstruction   summer   water: 10 weeks   started
                 
Road Improvements                
24th Street (Marine Drive to Haywood Avenue)   Road maintenance and road resurfacing   summer   5 days   not started
Finch Hill (Chippendale Road to Pinecrest Drive)   Road resurfacing   fall   2 weeks   not started
Skilift Road (Westhill Drive to Folkestone Way)   Corridor improvements: road resurfacing, sidewalk and curb   spring   6 weeks   started
24th Street and Bellevue Avenue railroad crossing   Grade crossing upgrade consisting of road approach improvement and installation of a gate   summer   3 weeks   started
Nelson Avenue and St. Georges Avenue   Intersection improvement   2016 carryover        
21st Street and Marine Drive   Traffic signal upgrade   2016 carryover       ongoing
Horseshoe Bay Streetscape   The Horseshoe Bay Streetscape will be constructed and completed in phasing, with one phase starting 2017   fall       not started
Hadden Drive Corridor Traffic Calming   Traffic calming to improve safety and reduce speeds       2 weeks   on hold
Whytecliff Park Pedestrian Path   A pilot program will be implemented this year which consists of creating walking space to Whytecliff Park through parking regulations   spring   1 week   not started
15th Street (Marine–Clyde)   Road maintenance: mill and pave   spring   1 week   not started
Sandy Cove; Eagle Island Sinclair Court   Bridge maintenance and bridge repair   spring   various   not started
Various bus stop improvements   As part of our joint initiative to improve pedestrian and transit infrastructure, various bus stop enhancements will be completed throughout the District   summer   various   not started
Marine Drive Bike Lane Pilot Project (25th–30th Streets)   The District is planning a pilot project for separated bike lanes along one section of Marine Drive   summer   2 weeks   not started
29th Street and Marine Drive intersection upgrade   Pedestrian signal upgrade   fall   2 weeks   not started
                 
Sewer & Drainage                
The Cove Lift Station replacement   Upgrade existing pump station   spring 2017   TBD   in progress since 2016
Citrus Wynd Treatment Facility upgrades   Sewage treatment facility upgrades   summer/fall   2 months    
Willow and Claymore Creek outfalls   Creek and foreshore drainage improvements, 3 separate projects:
-Willow Creek debris trap
-Willow Creek storm outfall
-Ross Crescent storm bypass
  summer 2017   8–12 weeks   design phase
2500 Palmerston Avenue sewer replacement   Replacement of sanitary and storm sewer mains through laneway and right-of-way between 2500 blocks of Palmerston Avenue and Queens Avenue   late summer/fall   TBD   in progress: restoration deferred to 2017
Sewer Rehab Program   Trenchless rehab of sanitary and storm sewer mains throughout the District   January/February 2018   12–14 weeks   not started
                 
Water                
Brothers Creek crossing   Water main upgrades to Brothers Creek crossing   summer/fall   12 weeks   completed 2017 segment
23rd Street (Kings Avenue to Mathers Avenue)   New water main installation   summer/fall   6 weeks   not started
800 Fairmile Road and Eyremount Drive   Water main upgrades   spring 2018   8 weeks   not started

 

×